Murdock Street is a narrow neighborhood street with little to no shoulder space along most of the roadway. Steep drainage ditches line the road in some spots, making walking space very limited. The City of Tigard desires to create a safe route along Murdock Street for both pedestrians and cyclists.
Construction Update - 4/15/2024
Construction of the Murdock Street and Stormwater project has been moved to start in the spring of 2025. During final design and permitting efforts, a utility determined that they wouldn’t be able to meet our expected timeframe for utility relocation to allow construction to being this summer. We are currently coordinating with the utility to limit the impacts to the public as much as possible. However, you may see utility relocation efforts begin as early as summer 2024.
Revised Schedule:
- Utility Relocations: Summer 2024 – Spring 2025
- Construction Bidding: January 2025
- Construction: Spring 2025
*Construction near the middle and elementary schools (below 100th Ave) will start once the school year has ended to limit impacts on students getting to school.
What's New?
- Recently added updated roll-map
- Check out the story map.
- Our project team will be reaching out to affected property owners to talk about the modified pathway and tree report
What is Planned?
- New 8-10' wide shared use path
- American with Disabilities Act (ADA) compliant ramps and other features
- Safer pedestrian crossings
- Improved access to and from Twality Middle School, Templeton Elementary School and East Butte Heritage Park
- New stormwater improvements
Project Drawings
These drawings with cross sections show specific project details.
Frequently Asked Questions
Read the summary of the September 8, 2022 Open House. Do you have questions about the project? Drop them in the form below and we'll get some answers.